Rebuilding Claysville and Vine Street
electric substations
GPS mapping of electric, water and
wastewater systems
Removal of duplicate electric
lines from system
Assume operations of Package WWTP
in Centerville
Rebuild Claysville and

In 1974 the Claysville Electric Substation was erected to add additional electric capacity to the City’s electric system. The 5000 KVA transformer is now underrated for the needs of the city and the substation is now being rebuilt by the City Electric Distribution Crew. A rebuilt 10,000 KVA transformer was purchased and set in place of the existing transformer. The rebuilt transformer cost about half of what a new transformer would have and the warranty being offered is three times longer than a new one.
The site itself was expanded to allow maneuverability within the
structure. The area has been graded out and a retaining wall erected on the North
and East sides. A new 8’ chain link fence surrounds the facility. A new
electric grid work has been installed 2’ in the ground, backfilled with earth
and rock. The two circuits fed from Claysville were back fed from our
The old 5000 KVA transformer was rebuilt for use at the

Claysville
Substation before upgrade

Thanks to TTI Railroad and Hinkle Construction for their help!

Setting the transformer in place

New 10KV transformer

Replacing insulators

Testing the transformer

Engineer Bob Brown overseeing the installation

Steve, Aaron and Wally “git’n’er done”

Vine Street Substation

Grounded For Safety.

TTI Railroad Loading Reconditioned Claysville 5,000 KVA
Transformer.

Chained Down For Transport.

Moving Courtesy of Hinkle Contracting.

Removing

Bringing in the Replacement.

Last Move.

In Place and Ready to Hook Up.

Installing 69KV Insulators.

New Switches and Insulators.

City, KU and 4-Way Electric workers wrapping it up.

Finishing up the Job.

The Paris Police Department has received eight new
Ford Crown











Trimble Recon Unit and Pathfinder Receiver

The City of Paris is in the process of
mapping its water, wastewater and electric utilities using the Pathfinder GPS
Trimble unit to locate different aspects ot the utility systems and then
exporting them into the ArcGis mapping program by ESRI Software. The system was
initially purchased through the efforts of former Communications Supervisor
Pete Clough who retired in 2006. The ESRI software is used in conjunction with
the E-911 Spillman program used for Central Communications.
The Trimble
Recon unit will allow all aspects of the utility systems to be properly mapped
and placed in their GIS co-ordinates on the State Plane map. Electrical poles,
transformers, capacitor banks, electric meters, substations, street lights,
fuses, cutouts, etc. as well as water line valves, fire hydrants, water meters,
manholes and lift stations will be easily located for emergency purposes and
data associated with each item will make the information available with the
click of the mouse.
sample map generated with ESRI’s ArcGIS

ESRI ArcGIS software

2nd and

6th and

6th and

7th and

7th and

8th and

10th and

Storefront

Original Lamp
Post Proposed

Last revised: 5/28/2008
10:35 AM
Send
comments and feedback to: pariskyitgis@adelphia.net